COUNCILLOR HUNT QUESTIONS - 3 |
HISTORICAL BREACH OF THE ENVIRONMENTAL PROTECTION ACT
question to: | illustrations: | info: |
Ceri Morris Question |
Overview: The planning department are attempting to cover up historical malpractice where they colluded with the Cuddy Group to hide contamination and a human health risk assessment in a series of planning applications between the period 2008 and 2010. This malpractice breached the 1990 Environmental Protection Act and the planning department are trying to hide this. Evidence was submitted to the Neath-Port Talbot Council Planning Committee and the Glynneath County Councillors Del Morgan and Simon Knoyle on 7/9/2020 in the below document and to date no counter evidence has been provided by the council. CLICK HERE TO VIEW THE EGRAC 1990 ENVIRIONMENTAL PROTECTION ACT BREACH REPORT CLICK TO SEE THIS DOCUMENT AS A YOUTUBE VIDEO Subsequent to this document being submitted to the NPT Council planning committee a second member of our residents group died from an extremely rare neurodegenerative disorder PSP that has been linked to Arsenic. The residents lived 5 doors apart and at the closest proximity to the site. Our 1990 EPA breach document provides evidence that an above safe level of the contaminant Arsenic was found at the site and left un-remediated against the advice of the human health risk assessment submitted to NPTC. A second document was created at submitted to Natural Resources Wales, Glynneath Town Council and Neath-Port Talbot Council that contained this information. CLICK HERE TO VIEW THE EGRAC PSP REPORT CLICK TO SEE THIS DOCUMENT AS A YOUTUBE VIDEO Question to Ceri Morris: In an email dated 4/5 2020 you stated that: "Turning specifically to the issue of land contamination at the site and whether the Council has historically contravened the Environmental Protection Act 1990, I would advise that this legislation no longer applies when a site is going through the planning process; by definition therefore the Council has not at any point contravened its duties under this legislation, as it is not relevant once the planning process has commenced." Please can you supply evidence that the council followed the Contaminated Land Strategy process in relation to the contamination identified in the 2008 chemical testing and human health risk assessment at the Heol y Glyn landfill. The UK law the Environmental Protection Act required either testing the site further to establish whether or not the site was a special site or remediation of the land as suggested in the human health risk assessment? The reason we ask this question is because: This statement by Ceri Morris is a deliberate mis-representation of a UK Government law. CLICK HERE FOR THE ORIGINAL DOCUMENT WRITTEN BY CERI MORRIS CLICK HERE FOR A YOUTUBE VIDEO THAT EXPLAINS THIS INCIDENT IN GREATER DETAIL CLICK HERE TO VIEW THE EGRAC 1990 ENVIRIONMENTAL PROTECTION ACT BREACH REPORT Further information: The Contaminated Land Officer identified that the testing in 2008 was inadequate during the planning committee meeting of 8/9/2020. Notes: Failure to provide evidence of correct contaminated land protocol by the developer Cuddy means that the council planning department worked together with the Cuddy Group Ltd to avoid the correct contaminated land protocol as required UK Government law, the 1990 Environmental Protection Act. |
THE CORPORATE MANSLAUGHTER OF GLYNNEATH / CWMTWRCH RESIDENTS
P2021/0153
Chemical testing |
7 October WAC sheets 12 October P2020/0863 submitted to remove the spoil heap without testing 13 October chem testing of the site. 16 March approved without going through the committee. My chemical analysis support team have identified the following corruption indicators in the chemical testing of 13 October 2020 undertaken by Terra Firma pre info |
|
Splitting of chemical testing. There is no valid reason why a developer or planning agent would split the testing. To test again in another area would incur unneccessary additional costs. A duplication of the testing effort would almost double overall cost of testing. Previous testing at the site has always been of the whole area so a partial testing of the site raises the question why? . |
||
If we refer to the text in this image we will see that: 'Shallow soil samples were taken from the top 600mm and in addition, deeper samples were collected to ascertain the nature of the deeper soils.' Then if we refer to the testing samples we will see that TP1-6 shallow sample is missing. If the deeper sample is contained on the spreadsheet then the shallow sample must have been submitted to the testing agent because it is inconceivable that they would start a trial pit and abandon the top layer as unsuitable once the pit is completed. If the top layer was unsuitable for testing the trial pit would not have been started or abandoned as unsuitable at an early stage. RED FLAG - If we look at the sequencing of the contamination we will see the potential reason why this sample is missing. In trial pits 1 and 2 we don't see a lower level, potentially this could be because the lower level was not unsuitable for extraction however, if we refer to trial pit 6 we will see there is no test recorded for the top layer of the soil. If we then refer to the level of contamination of the lower level of TP1-6 we will see a high level of contamination (1.3, 4.6, 3.5 & 8.75 above safety guidelines). Looking at the sequencing of the contamination in the remaining trial pits that have both samples recorded (3, 4, 5 & 7) we will see that in TP1-3 all the contamination is in the top layer, in TP1-4 the contamination in the top layer exceeds that of the lower sample, Only in layer 5 does the contamination in the lower level exceed the top layer, TP1-7 is inert. If we refer again to the information contained in the introduction to the chemical testing table: "'Shallow soil samples were taken from the top 600mm and in addition, deeper samples were collected to ascertain the nature of the deeper soils.' This would suggest that 14 samples were submitted to the testing agent and 3 have been removed from the final testing results. The document was created in Microsoft Word on the 3/11/2021, the properties suggest that it was created by Ian Henley. Any information received from Chemtest could have been altered by Terra Firma (Wales) Ltd or adjusted by Chemtest to suit the needs of the developer. We see evidence of tampering with the testing resuilts in the statement "Two exccedances of Aromatic TPH C8 – C10 were noted, although when corrected for the prevailing Organic Matter (>2.5%) do not exceed the guideline", this tampering is shown in the Microsoft Excel spreadsheet inserted into the document, we can see by the green triangles in the upper left hand corner in the bottom left of the spreadsheet that the information received from Chemtest has been tampered with by Terra Firma. A green triangle indicates an error in the formula. We have serious concerns about the integrity of the information in this document, we believe the reason the 3 samples are missing is because the contamination recorded in these samples is well above the safety guidelines and may present a real health hazard to the residents surrounding the development. Question: Are the planning department able to organise the original communications, presumably by email, containing the original chemical testing information sent by Terra Firma to Chemtest and from Chemtest to Terra Firma? |
||
END |
PLANNING DEPARTMENT BLOCKING AND MANIPULATION OF INFORMATION
RECENT BREACH OF THE ENVIRONMENTAL PROTECTION ACT
|
https://docs.planning.org.uk/20210218/184/QOOBOOFF00900/2yw0ieq1dnj99jo8.pdf - chemtest contamination doc dated June 2020 with logo at top of page missing from October 2020 Terra Firma document.
Search the website with Google |