PLANS OF DEATH Enzo Homes, Heol y Glyn Development, Glynneath. March 2021 Planning application & decision - P2020/0863 Removal of the chemical testing safety conditions for 22,000 cubic metres of contaminated spoil heap that is to be either removed from the site or re-distributed around the site to include moving it next to peoples homes.
|
The purpose of the plans P2020/0863 is to remove the safety requirement
for the chemical testing of an industrial waste spoil heap tipped by the
Demolition and Asbestos removal contractor Cuddy Group Ltd during the
period 2003-2016. The planning approval is linked to P2020/0195 and
P2021/0546. The planning approval was given on 16 March 2021 without
going through the committee process.
Despite the fact that: The land was previous tested and found to be contaminated in 2008. There are eye witness reports of barrels containing unknown substances being buried on site. Deaths have occurred next to the site of a rare disorder that can be linked to contamination. The area to be removed from the site had just been tested as contaminated, this information was not made available to the planning department. |
Just after the NPTC planning committee set the conditions to fully
test the land in September 2020 (P2020/0195) Enzo Homes submitted a
planning application to remove the main part of the spoil heap prior to
testing. This would have meant disturbing the ground and potentially
releasing dangerous chemicals into the atmosphere that may have affected
residents in the locality. As a group we placed 20 objections with the
planning department. (the planning website shows only 4). A local
chemistry graduate, not a member of our group also indicated with the
planning department that they wanted to represent the residents of the
area in the planning meeting.
The committee meeting of 16 March 2021 was cancelled so this application
was passed by the planning department head Ceri
Morris without having gone through the committee itself. The
contamination information and Waste Acceptance Criteria information
submitted with the subsequent application 2021/0546 had already been
published prior to this meeting but was not included in the application
documents. If we consider that this application was to remove the
requirement for testing for contaminated land and that testing of the land
had taken place but was not made available then it must be accepted by the
NPTC that this is a deliberate act of malpractice.
This planning permission allows Enzo Homes to remove 21,000 cubic metres of contaminated land from the site without first testing the soil. Enzo was already in possession of a document dated 3 November 2020 that showed the land was contaminated. (Terra Firma, October 2020) CLICK HERE TO VIEW THIS DOCUMENT |
submitted on 25/9/2020
validated by NPTC on 12/10/2020 Approved on 16/3/2021 |
Application to vary the wording of condition 36 (contaminated land desk-top assessment) and condition 37 (remediation strategy) of application P2020/0195 to allow the removal of the site spoil heap prior to the submission of the required details for compliance with the condition.
NPTC Planning Application Summary page P2020/0863 - CLICK HERE P2021/0863 - documents and information page - CLICK HERE |
|
objections submitted |
EGRAC submitted 20 objections to the NPTC planning department, the
planning website shows only 4 objections.
20230504R-EM-EGRA-NPTC-0863-obj - Mike Thomas objection 20230504R-EM-EGRA-NPTC-0863-obj - Jen Woodward objection |
|
16/3/21 | Decision - approval | P2020-0863-01-decision - Approval of Full Planning Permission with permission to remove the stockpiled material. Contaminated land. - pdf file = P2020-0863-01-decision |
summary by Ceri Morris |
The decision summary by Ceri
Morris includes
"Although the developer has breached conditions, by re-commencing work on site prior to |
|
supporting letter Geraint John Planning |
P2020-0863-02-supporting-letter - A letter from Luke Grattarola
of Geraint John Planning suggesting the change in conditions 36
& 37 "with the exception" of the stockpile.
pdf file = P2020-0863-02-supporting-letter |
|
site plan | P2020-0863-03-site-plan - blank map of the site with surrounding houses outlined. pdf file = P2020-0863-03-site-plan | |
spoil heap volume info | P2020-0863-04-spoil-heap - area of spoil heap (SK01) 21,000 cubic metres to be removed. It is an extremely conservative view of the spoil and clearly incorrect judging on the historical satelitte images and resident testimonies. - pdf = P2020-0863-04-spoil-heap |
NOT INCLUDED
36 & 37 conditions in 16/3/21 approval
36 Notwithstanding the submitted details, no further development shall commence on site, excluding the removal of any stockpiled material, until an assessment of the nature and extent of contamination affecting the application site area has been submitted to and approved in writing by the Local Planning Authority. This assessment must be carried out by or under the direction of a suitably qualified competent person in accordance with BS10175 (2011) 'Investigation of Potentially Contaminated Sites Code of Practice' and shall assess any contamination on the site, whether or not it originates on the site. The report of the findings shall include: (i) a desk top study to identify all previous uses at the site and potential contaminants associated with those uses and the impacts from those contaminants on land and controlled waters. The desk study shall establish a 'conceptual site model' (CSM) which identifies and assesses all identified potential source, pathway, and receptor linkages; (ii) an intrusive investigation to assess the extent, scale and nature of contamination which may be present, if identified as required by the desk top study;
(iii) an assessment of the potential risks to:
(iv) an appraisal of remedial options, and justification for the preferred remedial
option(s).
Reason: 37 No further development, excluding the removal of any stockpiled material, shall commence on site until a remediation scheme to bring the site to a condition suitable for the intended use by removing any unacceptable risks to human health, buildings, other property and the natural and historic environment shall be prepared and submitted to and approved in writing with the Local Planning Authority. The scheme shall include all works to be undertaken, proposed remediation objectives, remediation criteria and site management procedures. The measures proposed within the remediation scheme shall be implemented in accordance with an agreed programme of works.
Reason: |
IMAGE BANK
NPTC Planning Application Summary page P2020/0863 - CLICK HERE
P2020/0863 - documents and information page - CLICK HERE
NPTC PLANNING HOME - CLICK HERE
SEARCH PAGE FOR PLANNING APPLICATIONS - CLICK HERE
Search the website with Google |